Starting a tenant improvement in Los Angeles without LADBS permits can cost months of delays and significant penalties. Stop-work orders and fees that can double or triple your permit cost happen regularly when business owners skip permits or submit incomplete applications.

After managing hundreds of LADBS permits across Los Angeles County for commercial construction projects, the permit process is predictable when you understand requirements and timelines.

DISCLAIMER: This guide provides general information based on LADBS resources as of January 2026. Requirements and timelines are subject to change. Always verify directly with LADBS.

What Requires LADBS Permits?

Permit Required: Interior walls, electrical modifications, plumbing changes, HVAC alterations, structural modifications, occupancy changes, fire sprinklers, ADA upgrades.

Permit NOT Required: Paint, carpet replacement (like-for-like), cabinet refinishing, minor fixture replacements.

LADBS Permit Types

Express Permits (1-3 Days): Minor work. Apply via PermitLA. No plan review.

Counter Plan Check (2-4 Weeks): Small remodels. In-person application.

Expanded Counter Plan Check (3-6 Weeks): Multi-floor improvements. Via ePlanLA or in-person.

Regular Plan Check (2-6 Months): Large projects with structural engineering. Via ePlanLA.

Understanding Permit Costs

Fees vary by construction valuation, square footage, and scope—including plan check, building permits, and trade permits.

Get Accurate Costs: Use LADBS Fee Calculator

Or Contact Build Solutions: Call now at (424) 234-1881 for project-specific calculations and timeline estimates.

Getting Your LADBS Permit

Step 1: Create an Angeleno Account

Register at the Angeleno Account Portal

Step 2: Prepare Documentation

  • Architectural plans (architect/engineer stamped)
  • Trade plans (C-10 electrical, C-36 plumbing, C-44 HVAC)
  • Structural calculations (if needed)
  • Title 24 energy compliance
  • Owner authorization

Most commercial projects require architect stamps. Express permits may use contractor stamps. Consult LADBS for requirements.

Step 3: Check Planning Clearances

LADBS verifies clearances via Clearance Summary Worksheet:

  • City Planning approval
  • Fire Department (fire suppression)
  • Health Department (food service)
  • Historic Preservation (designated buildings)

Impact: Not addressing clearances early adds 3-8 weeks.

Step 4: Submit Application

  • Express: PermitLA (no appointment)
  • Plan Check: ePlanLA (organized PDFs)
  • In-Person: Schedule with printed plans

Step 5: Plan Check Review

Expect 2-3 correction rounds. Respond within 24-48 hours—slow responses cause most delays.

Step 6: Receive Permit

Pay fees online, download a permit, post on the site, and begin construction.

Required Inspections

Sequence: Foundation/framing, rough electrical, rough plumbing, rough HVAC, fire/life safety, final.

Schedule: Call 311 (LA) or (213) 473-3231. Allow 24-48 hours' notice.

Never cover work before inspection. Failed inspections require corrections and delays.

Fast-Track Office TI Program

LADBS offers expedited processing for office tenant improvements (launched October 2021).

Eligibility: Office only (not retail/restaurant/medical), existing buildings, non-structural, via ePlanLA, licensed professionals.

Benefits: Reduced timelines, priority review.

Verify: Contact LADBS at (213) 473-3231 for current availability.

Mixed-Use: LADBS evaluates occupancies separately and may require multiple permits.

Common Delays & Solutions

Incomplete Submissions (2-4 Weeks): Hire LADBS-experienced architects. Submit complete packages.

Missing Clearances (3-8 Weeks): Verify during design, not after submittal.

Slow Corrections Response (2-6 Weeks): Monitor daily. Respond within 24-48 hours.

Inaccurate Valuation (4-8 Weeks): Use realistic costs. Underestimation triggers audits.

Critical Mistakes

Starting Before Approval: Stop-work orders, doubled/tripled fees, demolition requirements.

Skipping Inspections: Voided permits, no Certificate of Occupancy.

Ignoring Violations: LADBS won't issue new permits until violations are corrected.

Timeline Expectations

  • Express: 1-3 days
  • Counter Plan Check: 2-4 weeks
  • Expanded Counter: 3-6 weeks
  • Regular Plan Check: 2-6 months

Tip: Build 3-6 month timelines. Never commit to lease dates before permits.

LADBS Contact

Office: 201 N. Figueroa Street, Los Angeles, CA 90012
Phone: 311 (LA) | (213) 473-3231

Resources:

Expert Permit Support

Build Solutions manages complete permit processes for LA tenant improvements. With 100+ permitted projects, we handle complexities so you focus on business.

Services: Application preparation, architect coordination, plan check management, clearances, inspections, and LADBS relationships.

Build Solutions, Inc.
Licensed #1047137 | WBE Certified

Call Now:  (424) 234-1881
Email:
natalia@buildsolutionsgc.com

Address: 1901 Avenue of the Stars, Suite 200, Los Angeles, CA 90067

View Our Completed Projects | Get Free Permit Consultation | Learn About Us  | About Natalia Piper

FAQs

How long does LADBS permit take? Express: 1-3 days. Counter: 2-4 weeks. Expanded: 3-6 weeks. Complex: 2-6 months.

Start before approval? No. Results in stop-work orders and significant penalties.

When need an architect? Most commercial projects require architect/engineer stamps. Express permits may use contractor stamps. Consult LADBS.

Failed inspection? Fix noted corrections, schedule re-inspection. Work stops until passing.

Information based on LADBS resources as of January 2026. Verify current requirements with LADBS.

Related News

View All
February 23, 2026
Development

2026 Commercial Construction Costs in Los Angeles

January 21, 2026
Development

7 Red Flags When Hiring a Commercial Contractor in Los Angeles (Don't Ignore These Warning Signs)

January 12, 2026
Development

How to Choose a Commercial Contractor in Los Angeles Without Getting Ripped Off

December 8, 2025
Development

Choosing the Right General Contractor in Los Angeles: A Complete Guide

November 25, 2025
Development

Why Core and Shell Construction Is a Smart Move Before Winters in Los Angeles

October 23, 2025
Development

What Is Tenant Improvement and Why Is It Important?

October 8, 2025
Inspiration

How to Find a Commercial Contractor That Won't Rip You Off?

September 12, 2025
Inspiration

The Hidden Dangers of Fake Reviews for Small Businesses: Insights from The New York Times

August 31, 2025
Inspiration

How to Choose a Good Commercial Roofing Contractor in Los Angeles

August 29, 2025
Development

Transforming Reseda: Build Solutions Completes $2M Core and Shell Redevelopment for Multi-Tenant Commercial Success

August 29, 2025
Development

Why Build Solutions Is Los Angeles’ Trusted Partner for Commercial Construction

August 12, 2025
Development

Best Commercial Contractors Near Me - Why Build Solutions is the Right Choice

July 24, 2025
Development

Ground-Up Construction: Tailored Solutions for Los Angeles Business Growth

July 14, 2025
Development

"Top 5 Reasons to Hire a Local Commercial Contractor in Los Angeles for Your Next Project"

June 17, 2025
Development

How Do I Find the Right Licensed Commercial Contractor?

May 23, 2025
Development

Why Hospital Renovation Is Critical for Patient Care and Compliance in Los Angeles

May 16, 2025
Design

Requirements to Be the Best Commercial Contractors in Los Angeles

May 9, 2025
Design

Attract More Customers to Your Restaurant with the Best Tenant Improvement in Los Angeles

May 2, 2025
Development

Leading Industrial Construction Contractors in Los Angeles – Build Solutions

April 29, 2025
Development

Why Tenant Improvement Is Important: Enhancing Value, Functionality & Satisfaction

April 17, 2025
Design

Top 2025 Commercial Renovation Trends: Building Smarter, Greener, and More Human-Centric Spaces

March 27, 2025
Development

The Ultimate Guide to Commercial Construction in Los Angeles: Trends, Costs, and Best Practices

March 17, 2025
Development

Importance of Office Renovation

March 4, 2025
Development

Why Build Solutions is the Best

February 24, 2025
Development

Office Restroom Facility Construction in Los Angeles: Excellence by Build Solutions

February 6, 2025
Development

Optimizing Office Facilities with Build Solutions in Los Angeles

December 19, 2024
Development

DBE Certified

December 16, 2024
Development

ACDBE certified

December 10, 2024
Development

Office Construction During the Holidays in Los Angeles

October 24, 2024
Design

Religious Facilities Construction in Los Angeles

October 23, 2024
Design

Retail Renovations in Los Angeles

October 18, 2024

Hospital Construction Contractors in Los Angeles

October 17, 2024
Development

Healthcare Facilities Construction in Los Angeles

October 14, 2024
Design

Restaurant Remodels in Los Angeles

October 8, 2024
Development

Ground-Up Construction in Los Angeles

October 7, 2024
Development

Tenant Improvement in Los Angeles

October 3, 2024
Design

Best Commercial Contractor in Los Angeles

September 29, 2024

Bringing warmth To Your Office Renovation in Los Angeles

February 10, 2024

Emerging trends In commercial construction Los Angeles

April 30, 2020

Level Up Your Commercial Space with A Pool